Continuing Job on Following Day

This function allows you to stop the job currently in progress, then continue it on the following day.

The job currently in progress and reserved jobs on standby can be restarted on the following day.

Tips
  • By turning on the sub power switch, jobs can be restarted on the same day.

  • Continuing jobs on the following day can be done when Image Controller IC-605 is mounted.

  1. Display the MACHINE screen, then press Stop on the control panel.

    A dialog is displayed to specify the settings for continuing the job on the following day.

  2. Press the JOB LIST tab.

    The Reserved Job screen is displayed.

  3. Press either Temporary Stop or Stop at a Set.

  4. Press Save Job List then Power OFF at the bottom-left corner of the screen.

    A dialog is displayed to confirm the power-off.

  5. To continue the jobs on the following day, press Yes.

    • supplementary explanationThe suspended and reserved jobs on the list will be stored.

    • supplementary explanationPress No to cancel continuing the job on the following day. The screen returns to the JOB LIST screen.

  6. Check the message displayed on the dialog, then turn off the sub power switch.

  7. To continue the jobs, turn on the sub power switch to display the MACHINE screen, and then press Start on the control panel.